Project Phase |
Recipes |
Cost |
Resources |
Tender / Bid in early design |
Fixed Durations or Parametric Level 2 (based on cycle times and/or production rate of material installed (SF/CY) |
Index cost for labor & equipment |
Can assign critical resources by scope or system to understand start and end dates (may not get true optimization of crews). Note: if don't assign a resource ALICE defaults to 24/7 calendar (apply calendar override). |
Tender / Bid in advanced design |
Fixed Durations or Parametric Level 2 (based on cycle times and/or production rate of material installed (SF/CY) |
Conceptual budget by system |
Can assign by crew types (if self-perform) or systems |
Preconstruction |
Fixed Durations or Parametric Level 3 (based on quantities and crew hours) |
Target budget break out by cost of material, labor, and equipment (index cost okay) |
All crews and equipment |
Buyout |
Fixed Durations or Parametric Level 3-4 (based on quantities and crew hours) |
Target budget, break out by cost of material, labor, and equipment (index cost okay) |
All crews, equipment, and materials |
Construction |
Fixed Durations or Parametric Level 3-4 (based on quantities and workforce hours) |
Target budget vs. actuals break out by cost of material, labor, and equipment (index cost okay) |
Critical equipment, materials, self-perform crews if any (recommended) |