In this article, you will learn the basic functionalities of the Plan page in ALICE Core. The Plan page is where users can build a schedule from scratch or make edits to an existing imported schedule. On the Plan page, users can add flexibility to the schedule so that projects can be further optimized on the Optimize page.
The key topics covered in this article will teach you how to use the Plan page:
- Plan Page views
- Types of Information Available
- Customize your View
- Modify your Plan
- Navigate the Schedule
- From Plan to Optimize and Analyze
Plan Page views
There are 3 main views on the Plan page: Gantt, Canvas and Timelapse.
This article focuses primarily on the Gantt view and interacting with tasks in your schedule in a 1D view.
Check out the Canvas article to learn how to plan visually on a 2D canvas and create an animated Timelapse.
Types of Information Available
Below are the types of information available for each task in the Gantt schedule. The information can be displayed as additional columns in the Gantt schedule.
- WBS
- ID
- Name
- Status
- Remaining duration
- Duration formula
- Actual duration
- Budgeted labor units, Actual labor units, Remaining labor units
- Start, Finish
- Planned start, Planned finish
- Actual start, Actual finish
- Early start, Early finish
- Late start, Late finish
- Suspend, Resume
- Constraint
- Calendar
- Crews
- Workforce
- Materials
- Equipment
- Predecessors
- Successors
- Total float
- Free float
- All Custom Properties (or User Defined Fields, UDFs)
Customize your View
The Plan page can be modified to show you the information that is most relevant to your needs.
Click the cog icon in the upper right corner to access the Plan page settings menu. From here you will see 3 tabs:
General:
Duration and float units: toggle workdays or work hours.
Date format: select date only or date and time.
Duration round up: To automatically round up task durations created from formulas or crew ranges, define a round up interval (learn more).
Table Columns:
Modify which columns appear on the Plan page. From this view you may select, hide and drag to re-order your visible columns.
Gantt:
Show critical tasks toggle
Show longest path toggle
Show WBS gaps toggle
In addition to the settings menu, you can interact directly with the Plan page to modify the following:
- To resize the width of the columns, you can click on the line that separates two cells in the header row to adjust the size, similar to how you would adjust a column width in Excel.
- To expand the table view and minimize the Gantt view, click 'show all columns' or hover your mouse over the vertical divider and drag to customize where the two views split.
All these settings will be auto-saved by ALICE and appear next time you open the Plan page.
Group and Sort Tasks
The tasks in a plan may be grouped and sorted by different categories:
- WBS - native WBS structure imported from Primavera P6 or Microsoft Project
- Crews - grouping by crew type
- Blocks - if you have created visual blocks in the canvas view, you can group your schedule by blocks.
- Detected Cycles - If ALICE detects circular logic, you can filter to view tasks that are in that logic cycle.
- Custom - grouping by any combination of resources or custom Properties (UDFs). The order that you input the custom categories will determine the grouping order.
- Sorted - order your tasks by date, float, name or float.
Tip: Tasks can be dragged and dropped to different WBS sections if the schedule is sorted by the WBS view.
For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:
How to Group and Sort Tasks
- In the Gantt chart, open the Group by dropdown list from the upper-left side of the page.
- Select the grouping category desired.
Create Filters and View Select Information
The Plan page comes with a powerful filter tool that allows you to find the right information in your schedule. Filters are helpful for schedule analysis, resource assignment, and bulk removal of preferential logic.
Click the filter builder to filter data by many different categories, as shown below. The filter builder supports AND/OR logic.
Filters:
- On the Gantt Chart, click on Select to Filter on the upper-left side of the page.
- ALICE allows the use of the following categories to filter the Gantt:
- Crew
- Criticality: Critical Tasks and Longest Path
- Custom Properties / UDFs
- Equipment
- Material
- Task Name/Codes
- Task Status: Not Started / In Progress / Completed
- Task Type: Task, Start Milestone, Finish Milestone, Level of Effort
- After selecting the categories, define the filter logic:
- OR logic filters the activities that at least have one of the selected items
- AND logic filters the activities that have all selected items
- Click Done to apply the filter.
- To remove the filter, click on the X next to the filter name.
How to Collapse and Expand WBS
To collapse or expand to the desired level of your WBS, right-click anywhere in the Plan page and make your selection. You can also collapse or expand all from the menu below.
Additionally, this menu can also be used to add new tasks, duplicate existing tasks, or delete tasks.
Modify your Plan
On the Plan page you can add, edit or remove tasks, WBS, LOE and milestones (rows), and input data about them (columns).
Undo/Redo
Along the bottom of the Plan page you will see an action bar with Undo/Redo icons. Up to 100 of your past actions can be undone. Undo/Redo are compatible with the universal keyboard shortcut commands, see Keyboard shortcuts for details.
Add New WBS, Level of Effort (LOE), Tasks, and Milestones
- Right click on the row or area where you wish to add the new data
- Click Add New
- Select desired data type and input a name
- The new WBS will appear at the bottom of the list
right click to select Add new
Add/Edit Calendars or Custom Properties
- To add or edit tasks one row at a time, right click the desired row and select add/edit.
- To add or edit multiple rows at once, select the checkbox next to each task that you wish to edit and then select add/edit. You can select the checkbox next to a grouping to select all rows within that grouping.
Add/Edit Logic Relationships between Tasks and Milestones
- Predecessors and Successors can be defined from the plan page via the predecessor or successor columns.
- Relationships can also be drawn via click and drag on the Gantt view. ALICE will assume relationship type based on how it is drawn (IE from the finish of one task to the start of another will be a finish to start relationship), but it can always be modified by the user.
- Contained relationships can be added or removed in bulk my multi-selecting the desired rows and right clicking to access the contained relationship menu.
- Read this article for a deep dive on working with logic ties in ALICE.
Add/Edit Constraints to Tasks/Milestones
- Constraints can be added to rows on the plan page via the constraint column. Constraints may include a data and a time.
- Read this article for a deed dive on constraints in ALICE.
Updating Progress for Schedules in Execution
- Users can update status, progress, remaining duration from the plan page by inputting data directly into those columns. Single or bulk updates are supported.
- The data date can also be updated from the settings menu on the plan page.
- Read this article for detailed information about updating progress in ALICE and how these fields connect to each other.
Keyboard Shortcuts
The Plan page supports keyboard shortcuts to make navigation easier.
- Left, right, up and down keyboard arrows move to different cells
- Enter will select a cell and open it for editing
- When editing a cell, up and down arrows can be used to increment values or choose from a drop-down.
- After editing a cell, Enter will save changes
- In the cell edit window, Esc will exit without saving changes
- Left and right keyboard arrows move inside the current cell, if a cell is selected
- Undo/Redo:
- [Ctrl + Z] to undo and [Ctrl + Y] (or [Ctrl + Shift + Z]) to redo on Windows.
- On a Mac, use [Cmd + Z] to undo and [Cmd + Shift + Z] to redo
Edit Data Via Excel Export/Import
Bulk editing of data via Excel is supported by ALICE Core. Click the "Edit Data in Excel" button in the top right of the Plan page in order to use this feature. For a deeper dive into how to use this feature, click here.
Navigate the Schedule
Use tools in ALICE to navigate and understand your schedule at a deeper level.
Task Relationship Details Panel
Click on any task to open the task relationship details panel, located at the bottom of the screen. This powerful view shows everything you need to know about the task and how it drives the schedule. You can view predecessor and successor information, time gap, free float, total float and criticality.
Isolate Path, Critical Tasks or Longest Path for any task or milestone:
- Right click on any task or milestone
- Select "Paths"
- Select Isolate Path, Isolate Critical Tasks or Isolate Longest Path
Filter for Critical Tasks and Longest Path
- From the settings menu, you can toggle to view critical tasks and the longest path.
- To view near-critical tasks, you can filter to bound a minimum and maximum for total float and show tasks within that bound.
Please see this article to learn more about how to work with critical tasks and longest path in ALICE.
Zoom In/Out, Toggle Relationship Arrows in Gantt View
The icons at the bottom of the Plan page allow the user to control:
- Magnify glass icons: Level of zoom on the Gantt view
- Arrow icon: Toggle to show or hide relationship logic arrows
- Up arrow icon: is a shortcut to scroll to the top of the page
From Plan to Optimize and Analyze
- After making modifications on the Plan page, click the Re-schedule button in the top right corner to schedule the tasks with CPM - this is akin to the F9 button in P6.
Tip: The Re-schedule button only appears if there are changes in the plan since it was last scheduled. - After re-scheduling you have two options:
- Navigate to the Optimize page to create optimized schedules (Optimize customers only): Proceed to the Optimize page by clicking Optimize on the left navigation menu and create scenarios based on the plan you created. When you generate schedules from the scenario builder on the Optimize page, they are scheduled with the ALICE optimization algorithm which automatically explores a multitude of possible solutions and surfaces the optimal solutions.
- Click 'Add Scenario' to view your CPM schedule on the Optimize page without Optimizing: It is possible to directly add the current schedule on the Plan page to the Optimize page with the Add Scenario button. When you use this button, it will bypass the ALICE scheduling and optimization algorithm, and only CPM will be used to generate the schedule. This is useful if you’re trying to pin down a baseline and compare the schedule before optimization versus after ALICE optimization.