This article outlines everything you need to know about creating and assigning calendars in ALICE.
Creating Workweeks
Before you can create a calendar, you need to create a workweek. A workweek outlines the working hours and the overtime hours (if applicable) for a single week for the calendar you are about to create. A calendar may use multiple workweeks at different times of the month/year.
For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:
Create Workweek:
- In the Resources tab located in the upper right, go to the Calendar section.
- Under the Calendar section, switch to Workweek
- Enter the workweek name and click Create Workweek
- Click Add Normal Hours to add daily working hours
- Move the blue bars to adjust the working hours - repeat the same for every working day required
Add Overtime Hours:
- Increase the salary rate multiplayer next to "Add Normal Hours."
- ALICE will calculate the resource salary based on the multiplier applied to each workday
- Click "Add Overtime Hours" and use the bars to adjust it according to project requirements.
Creating Calendars
Once workweeks are created and defined, you are ready to create calendars.
For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:
Create Calendar:
- In the Resources tab located in the upper right, go to the Calendar section.
- Click Create Calendar
- By clicking on the first date, ALICE will select the range from the selected date to infinity.
- Once the range is selected, click Assign to assign the required Calendar from Project Workweeks.
- To select a specific range, select the first date, hold the SHIFT key, select the last date, and Assign the required project workweek.
- Enter the calendar name, and click Save to complete the process.
Assigning Calendars on The Plan Page
Once calendars are created, you are ready to assign calendars to activities on the Plan page.
For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide: