Tutorial: Crew, Equipment and Material (bulk) Assignment

If you are looking for instructions on assigning Crew to your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

 

Crew, Equipment and Material Assignment:

  1. In the Gantt chart, "right-click" and select "Edit Columns."
  2. Select "Crews", "Equipment" or "Materials" and click "Done" to add the columns to the Gantt chart.
  3. Double-click on the cell of respected resource colulmn to open the assignment window.
  4. Define the type and number of resource, and click Save to complete the process.

Crew Range:

  1. Crew range is a unique functionality of ALICE that identifies the optimal number of crews required to achieve project objectives.
  2. In the crew assignment window, define the minimum and maximum number of crews allocated for that activity.
  3. Click Save to complete the process.

Bulk Assignment:

  1. To ease the bulk assignment, use the Filter tool.
  2. Go to "Task/Names" and filter for operations that share the same resources.
  3. Select All and click Done to apply the filter.
  4. Select all activities by clicking on the WBS summary
  5. On the upper-left corner, click on "Resource Assignment" functionality
  6. Select Crew, Equipment or Material assignment
  7. Define the type and number of resource, and click Save to complete the process.