Tutorial: How to assign Equipment in ALICE Core

If you are looking for instructions on assigning Equipment to your ALICE projects, then you are in the right place!

Click through the player for an interactive walk-through, or scroll down for a step-by-step guide:

 

Equipment Assignment:

  1. In the Gantt chart, "right-click" and select "Edit Columns."
  2. Select "Equipment" and click "Done" to add the Equipment'sEquiumn to the Gantt chart. 
  3. Double-click on the equipment cell to open the assignment window.
  4. Select the required Equipment, define the number of Equipment, and click Save to complete the process.