Tutorial: Assign Constraint Type and Date (Milestones) in ALICE Core

If you are looking for instructions on how to assign Constraints to your ALICE projects, then you are in the right place!

Click through the player for an interactive walk-through, or scroll down for a step-by-step guide:

 

Constraint Assignment:

  1. In the Gantt chart, "right-click" and select "Edit Columns."
  2. Select "Constraint Type" and "Constraint Date" and click "Done" to add the column to the Gantt chart. 
  3. Double-click on the Constraint Type cell to open the assignment window.
  4. Select the required constraint type.
    • As late as possible 
    • Start On
    • Start On or After
    • Start On or Before
    • Mandatory Start
    • Finish On
    • Finish On or After
    • Finish On or Before
    • Mandatory Finish
  5. Click Save to complete the process.
  6. Double-click on the Constraint Date cell to open the assignment window.
  7. Select the required date for this specific activity or milestone.
  8. Click outside of the calendar window or click ENTER to complete the assignment process.
Was this article helpful?
0 out of 0 found this helpful