P6 and MSP schedules with actualized tasks can be imported into ALICE Optimize. Read on to learn how actualized data is handled in ALICE.
With the import actualized data feature, users can:
- Import a project in preconstruction with some completed work and simulate, optioneer or optimize all future work
- Import a project in execution and determine how to respond to a change such as a milestone delay or a design change
- Import a delayed project and use ALICE to explore recovery scenarios
In all of the above cases, the ALICE resource optimization and scheduling algorithm will intelligently operate only on the work not yet done. Read on to learn more about the technical fundamentals and things to keep in mind when importing a schedule that includes actualized tasks.
Interested in importing an updated version of a schedule you have already run in ALICE? Check out schedule sync.
Imported Fields
As part of the import, ALICE will identify:
- Task status: not started, in progress, complete
- Actual start and actual finish dates
- Suspend and resume dates
- Data date
These data points are taken into account by the ALICE scheduling and optimization algorithm as detailed below.
Handling of complete, in-progress and not started tasks
- Imported tasks that have an “actual start” or “actual finish” value, or have the task status “Complete” are considered as actualized tasks in ALICE.
- If an imported task has both planned and actual dates, ALICE will use only the actual dates when scheduling that task, and will disregard the planned dates.
- Imported tasks with no actual dates will be scheduled using the imported planned dates.
- ALICE will indicate whether actual or planned dates are utilized.
Out-of-sequence work
For many valid reasons, tasks in a schedule may start, complete or be suspended without conforming to their precedence logic. When this occurs, a task will appear as "split" in the gantt view.
For imported P6 schedules, ALICE uses the retained logic approach to respecting precedence relationships between tasks. If a task has been started, completed or suspended out-of-sequence, any remaining work will be scheduled in conformance with the precedence logic for that task. It is not possible to override this setting in ALICE for imported P6 schedules.
For imported MSP schedules, ALICE uses the same logic used by Microsoft Project to handle out of sequence work.
For schedules created "from scratch" in ALICE, the retained logic approach will be used. If you wish to plan from scratch in ALICE and use MSP logic, you may import an empty MSP schedule to create the new project, which will trigger ALICE to use MSP logic.
Suspend and resume values
ALICE Optimize's implementation of retained logic also fully supports suspend and resume values. ALICE respects these values when it generates new schedules for customers.
- If a task has Suspend and/or Resume values, they will appear as read-only on the Plan page.
- For scheduling purposes, the actual end of the completed part is either the Data Date or the Suspend date.
- If a Resume date is available, the Early Start value needs to be on or after the Resume date.
- You can hover over the task in the plan page to see the Suspend or Resume dates, if they exist
Resource Assignment and Scheduling for Schedules with Actualized Work
The ALICE scheduling and resource allocation algorithm operates on work that has not yet happened - this includes tasks not yet started, or the incomplete portion of in-progress tasks.
The duration formulas only operate on not started tasks. For in progress or completed work, durations must be static (numerical, not formula-driven).
- ALICE will not assign equipment, material, or crews to work that has been completed.
- Similarly, on the Optimize page, completed milestones will not appear as available for optioneering.
Modifying Data related to Actualized Tasks in ALICE
From the Plan page, users can modify data on not yet started tasks, and in some cases may modify the data related to in-progress tasks. Users cannot modify data on completed tasks.
Editable for not started tasks only:
- Calendars
- Crew Assignment
- Duration
Editable for not started or in-progress tasks:
- Equipment
- Materials
Frequently Asked Questions
Q: With actualized task support, does this mean I can use ALICE to manage my projects in execution?
A: With this feature, you can be confident that ALICE won’t unrealistically schedule or assign resources to work that is already in the past, and that your precedence logic will be respected. This opens up many exciting applications on projects in progress - especially projects at risk of delay and in need of recovery, or projects with change orders that impact the schedule. With that said, we are actively building additional features to better support the needs of projects in execution. Reach out if you would like to share your requests with our product development team.
Q: What is retained logic?
A: Here’s a link to an explainer we find helpful.