Tutorial: How to use Filters in ALICE Core

If you are looking for instructions on using Filters on your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

Filters:

  1. On the Gantt Chart, click on Select to Filter on the upper-left side of the page.
  2. ALICE allows the use of the following categories to filter the Gantt:
    • Crew
    • Criticality: Critical Tasks and Longest Path
    • Custom Properties / UDFs
    • Equipment
    • Material
    • Task Name/Codes
    • Task Status: Not Started / In Progress / Completed
  3. After selecting the categories, define the filter logic:
    • OR logic filters the activities that at least have one of the selected items
    • AND logic filters the activities that have all selected items
  4. Click Done to apply the filter. 
  5. To remove the filter, click on the next to the filter name.