Tutorial: How to use Filters on the Plan and Analyze Page

If you are looking for instructions on using Filters on your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

Filters:

  1. On the Gantt Chart, click on Select to Filter on the upper-left side of the page.
  2. ALICE allows the use of the following categories to filter the Gantt:
    • Crew
    • Criticality: Critical Tasks and Longest Path
    • Custom Properties / UDFs
    • Equipment
    • Material
    • Task Name/Codes
    • Task Status: Not Started / In Progress / Completed
  3. After selecting the categories, define the filter logic:
    • OR logic filters the activities that at least have one of the selected items
    • AND logic filters the activities that have all selected items
  4. Click Done to apply the filter. 
  5. To remove the filter, click on the next to the filter name.
Was this article helpful?
0 out of 0 found this helpful