Tutorial: How to review Relationship Details in ALICE Core

If you are looking for instructions on how to review the activity Relationship Details in your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

 

Review Relationship Details:

  1. On the Gantt Chart of Analyze page, select a task to activate the Relationship Details
    • Once selected, the Relationship Details will appear at the bottom of the page
  2. In the Relationship Details, users can review: 
    • Free and Total Slack
    • Predecessors and Successors 
    • Driving and Critical tasks
    • Reasons
      • Precedence is the standard relationship type defined by users such as FS, SS, FF, and SF.
      • Resource is the resource link generated by ALICE based on resource assignment. This applies to crews, equipment, materials, and milestones.
    • Time Gap is the duration or float associated with previous (predecessor) and subsequent (successor) activities.
    • Go to the previous (predecessors) or next (successor) of the selected task by clicking Select. 
Was this article helpful?
0 out of 0 found this helpful