Tutorial: How to Isolate Path

If you are looking for instructions on how to Isolate Paths in your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

 

Isolate Path:

  1. In the Gantt chart, hover the mouse courses on the task and "right-click" to open task settings.
    • You can hover the mouse cursor on the task name or on the timeline bar
  2. In the settings window, click Isolate path
  3. Isolate Path will filter all predecessor and successor tasks and milestones, directly and indirectly associated with the selected task.
  4. Click on the "X" to remove the isolate path filter.