Tutorial: How to group the Gantt in ALICE Core

If you are looking for instructions on how to group the Gantt chart in your ALICE projects, then you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

 

Gantt Grouping:

  1. In the Gantt chart, open the Group Gantt by dropdown list from the upper-left side of the page.
  2. ALICE allows 4-main grouping types:
    • WBS - native WBS structure imported from Primavera P6 or Microsoft Project
    • Sorted - grouping by chronological order
    • Crews - grouping by crew type 
    • Custom - grouping by Custom Properties / UDFs

Custom Grouping:

  1. From the dropdown list, select Custom.
  2. In the window, click on the blank field to open the list of available Custom Properties/UDFs to use for custom grouping.
    • To select multiple properties, use the button to add one after the other
    • The order in which the properties are added determines the Gantt grouping
  3. Select one or multiple properties/UDFs and click OK to apply the grouping.
Was this article helpful?
0 out of 0 found this helpful