Tutorial: How add Indirect Cost

If you are looking for instructions on adding Indirect Costs to your ALICE projects, you are in the right place!

For a more hands-on experience, navigate through the player for an interactive walk-through, or if you prefer a more detailed approach, scroll down for a step-by-step guide:

 

 

Add Indirect Cost:

  1. On the Plan page, go to Resources, located on the upper-right side of the page
  2. Under the Indirect Costs section, click + Add Cost
  3. Enter the following data:
    • Name
    • Daily Flat Rate / Cost
  4. Click Create Indirect Cost to complete the action and exit from Resources
  5. Click Re-Schedule to recalculate the schedule, and then Solutions to enter the Explore page
  6. On the Explore page, click + Create New Scenario, define the scenario name, and click Run Scenario
  7. Select the new dot to open the scenario summary
  8. Navigate to the Cost Breakdown section to review the Total Indirect Cost

NOTE: Total Indirect Cost is calculated by the Daily flat rate/cost multiplied by the project's Total Calendar Days

Was this article helpful?
0 out of 0 found this helpful