When ALICE ingests a P6 file, all the data from that file is stored in ALICE even though ALICE only uses some of that data for schedule manipulation and optimization. For the schedule data that ALICE does not show or use for calculations, it will be untouched and included in the export file exactly as it was included in the import file.
This article includes a dictionary of all fields included in the import and export, whether they are shown in ALICE or not, and any differences in field names between ALICE and P6.
Task fields shown
The table below aims to visualize all Imported, Exported and Shown task fields currently available between ALICE and Primavera P6.
ALICE |
Primavera P6 |
Task Fields |
|
WBS |
WBS Name |
ID |
Activity ID |
Name |
Activity Name |
Status |
Activity Status |
Planned Duration |
Original Duration |
Planned Duration Formula |
N/A |
Actual Duration |
Actual Duration |
Remaining Duration |
Remaining Duration |
Budgeted Labor Units |
Budgeted Labor Units |
Start |
Start |
Finish |
Finish |
Planned Start |
Planned Start |
Planned Finished |
Planned Finished |
Actual Start |
Actual Start |
Actual Finish |
Actual Finish |
Suspend |
Suspend Date |
Resume |
Resume Date |
Early Start |
Early Start |
Early Finish |
Early Finish |
Constraint |
Primary Constraint Date / Type |
Calendar |
Calendar |
Crews (Assignment) |
Budgeted Unit/Time |
Workforce |
N/A |
Materials (Assignment) |
Budgeted Unit |
Equipment (Assignment) |
Budgeted Unit/Time |
Predecessors |
Predecessors |
Successors |
Successors |
Total Float |
Total Float |
Free Float |
Free Float |
Late Start |
Late Start |
Late Finish |
Late Finish |
Custom Property |
Activity Codes - EPS |
Activity Codes - Global |
|
User Defined |
|
Task Relationship Details |
Predessors Details |
Successor Details |
|
Resource Logic (Task Relationship Details) |
Notes to Resources |
Resource fields shown
The table below aims to visualize all Imported, Exported and Shown resource fields currently available between ALICE and Primavera P6.
ALICE |
Primavera P6 |
Resource Fields |
|
Subcontractor Name |
N/A |
Trade |
N/A |
Crew Name |
Resource Name |
Imported Resource Peak |
N/A |
Max Units/Time |
Max Units/Time |
Default Units/Time |
Default Units/Time |
Prs/Crew |
N/A |
$Crew/Hr |
Standart Rate |
Calendar |
Calendar |
Idle Cost |
N/A |
Equipment Name |
Resource Name |
Equipment Quantity |
Max Units/Time |
Equipment $/hr |
Standart Rate |
Equipment Idle Cost |
N/A |
Material Name |
Resource Name |
Material Type |
N/A |
Material Quantity Available |
Budgeted Units |
Material $/Unit |
Standart Rate |
Production Rates |
N/A |
Indirect Cost |
N/A |
Task fields not shown
The table below aims to visualize all task fields not supported/shown in ALICE. This means that the following fields are saved in the file, and are exported back to P6 as it is, without any changes.
Costs |
Actual Expense Cost |
Actual Labor Cost |
Actual Material Cost |
Actual Nonlabor Cost |
Actual This Period |
Actual This Period |
Actual This Period |
Actual Total Cost |
At Completion Expense |
At Completion Labor |
At Completion Material |
At Completion Nonlabor |
At Completion Total |
BL Project Expense |
BL Project Labor |
BL Project Material |
BL Project Nonlabor |
BL Project Total |
BL1 Expense Cost |
BL1 Labor Cost |
BL1 Material Cost |
BL1 Nonlabor Cost |
BL1 Total Cost |
Budgeted Expense Cost |
Budgeted Labor Cost |
Budgeted Material Cost |
Budgeted Nonlabor Cost |
Budgeted Total Cost |
Remaining Expense Cost |
Remaining Labor Cost |
Remaining Material Cost |
Remaining Nonlabor Cost |
Remaining Total Cost |
Variance - BL |
Variance - BL |
Variance - BL |
Variance - BL |
Variance - BL |
Variance - BL1 |
Variance - BL1 |
Variance - BL1 |
Variance - BL1 |
Variance - BL1 |
|
Dates |
Anticipated Finish |
Anticipated Start |
BL Project Finish |
BL Project Start |
BL1 Finish |
BL1 Start |
BL2 Finish |
BL2 Start |
BL3 Finish |
BL3 Start |
Expected Finish |
External Early Start |
External Late Finish |
Remaining Early Finish |
Remaining Early Start |
Remaining Late Finish |
Remaining Late Start |
Secondary Constraint Date |
|
Durations |
At Completion Duration |
BL Project Duration |
BL1 Duration |
Remaining Float |
Variance - BL |
Variance - BL |
Variance - BL |
Variance - BL1 |
Variance - BL1 |
Variance - BL1 |
|
Earned Value |
Accounting Variance |
Accounting Variance - Labor Units |
Actual Cost |
Budget At Completion |
Budget At Completion - Labor Units |
Cost Performance Index |
Cost Performance Index - Labor Units |
Cost Variance |
Cost Variance - Labor Units |
Cost Variance Index |
Cost Variance Index - Labor Units |
Earned Value Cost |
Earned Value Labor Units |
Estimate At Completion Cost |
Estimate At Completion - Labor Units |
Estimate To Complete |
Estimate To Complete - Labor Units |
Planned Value Cost |
Planned Value Labor Units |
Schedule Performance Index |
Schedule Performance Index - Labor Units |
Schedule Variance |
Schedule Variance - Labor Units |
Schedule Variance Index |
Schedule Variance Index - Labor Units |
To Complete Performance |
Variance At Completion |
Variance At Completion - Labor Units |
|
Feedback |
Feedback from Resources |
New Feedback |
|
General |
Activity Leveling Priority |
Activity Type |
Added By |
Added Date |
Auto Compute Actuals |
Critical |
Critical Path Number |
Duration Type |
Est Weight |
Last Modified By |
Last Modified Date |
Lock Remaining |
Longest Path |
Owner |
Primary Resource |
Project ID |
Project Name |
Project Status |
Secondary Constraint |
Unread Comments |
WBS |
WBS Category |
WBS Path |
|
Lists |
Cost Account IDs |
Cost Accounts |
Resource IDs |
Resources |
Role IDs |
Roles |
Work Products and |
|
Multiple Float Paths |
Float Path |
Float Path Order |
|
Number of Activities |
Activity Count |
Activity Resource Assignment |
Actual Completed Activities |
Actual In-Progress Activities |
Actual Not-Started Activities |
BL Project Completed |
BL Project In-Progress |
BL Project Not-Started |
BL1 Completed Activities |
BL1 In-Progress Activities |
BL1 Not-Started Activities |
|
Percent Completes |
Activity % Complete |
Cost % Complete |
Cost % of |
Duration % Complete |
Duration % of |
Expense Cost % |
Labor Cost % |
Labor Units % |
Material Cost % |
Nonlabor Cost % |
Nonlabor Units % |
Percent Complete Type |
Performance % Complete |
Performance % Complete |
Physical % Complete |
Schedule % Complete |
Units % Complete |
|
Project Codes |
|
Units |
Actual Labor Units |
Actual Nonlabor Units |
Actual This Period |
Actual This Period |
At Completion Labor |
At Completion Nonlabor |
BL Project Labor |
BL Project Nonlabor |
BL1 Labor Units |
BL1 Nonlabor Units |
Budgeted Nonlabor Units |
Remaining Labor Units |
Remaining Nonlabor Units |
Variance - BL |
Variance - BL |
Variance - BL1 |
Variance - BL1 |
|
Activity Steps |
Activity Step Count |
Steps Completed |
Steps In Progress |
Steps Not Started |
Resource fields not shown
The table below aims to visualize all resource fields not supported/shown in ALICE. This means that the following fields are saved in the file, and are exported back to P6 as it is, without any changes.
General |
Active |
Assigned to Current Project |
Auto Compute Actuals |
Calculate costs from units |
Currency Name |
E-Mail Address |
Employee ID |
External Rate |
Internal Rate |
Office Phone |
Other Phone |
Overtime Allowed |
Overtime Factor |
Price / Unit4 |
Price / Unit5 |
Primary on Current |
Primary Role |
Resource ID |
Resource Notes |
Role IDs |
Roles |
Shift |
Title |
Unit of Measure |
User Login Name |
|
Resource Codes |
|
User Defined |