On July 31st 2025, a major system upgrade was released in ALICE Model (Pro).
This upgrade brings:
- Faster performance across the board
- Immediate access to new features previously exclusive to Optimize (Core)
- A modernized architecture that enables us to deliver new functionality even faster going forward
- Improved data interoperability between Model and Optimize
New Features and Benefits
Key Changes
Data Migration
New Features and Benefits
Explore page
- Faster page loads due to architectural improvements
- Faster input review and snapshotting
- Cross plan Explore page
- Scheduler keeps only one best solution
- Solution graph
- Custom solution graph axes
- Numbering solution
- Solution popover
- Project baseline
- Cost breakdown
- More metrics
- Compare solutions modal
- Compare modal CSV report
- Detailed comparison
- Comparison report CSV
- Create scenario
- Project end date constraint replaces Maximum duration
- Optimize using existing is removed
- Add optimization presets
- Person per crew was removed
- Drawer width was increased
- New milestone tab
- User can change constraint type
- Added time
- Configurable display settings for milestone task ID and WBS
- Milestone types changed to match ALICE Optimize and P6
- New algorithm selection for workflow
Analyze page
- No unpacking solution step
- Faster page loads due to architectural improvements
- Filters
- Page is not freezing when filters are applied on large project
- Added task type filter
- Added total float filters
- Element and Group filters work together - was producing empty results previously
- Exports
- Unified export experience with ALICE Optimize
- New option to export to P6 XER
- New option to export to MSP
- Export toggles for P6 and MSP was brought to ALICE Optimize and simplified
- There is now option to exclude resource logic for ALICE Optimize
- CSV export file format was unified with ALICE Optimize
- New option to print to PDF
- Gantt
- Crew, material and equipment individual columns are now merged into single columns like in ALICE Optimize
- Added option to show criticality with or without resource flow
- Bottom bar
- Relationship details
- Height is now resizable (It is saved between page loads.)
- UI is unified with ALICE Optimize
- Predecessors/Successors can be seen at the same time
- Task cards
- Improved design
- Gantt Only view has now task cards as well
- Relationship details
- Analytics
- Bar graphs grouped by day for better visibility
- Added peak workforce utilization graph
- Split daily material consumption and cumulative material consumption graph
- Cranes have their own category in cost over time graph
- CSV exports has same format as ALICE Optimize
- Date format changed from 14-Jul-2023 to 2023-07-14
Coming soon features
- Time varying capacities (ramp resources up or down over time)
- New Analytics
Omitted features
- Canvas
- LLM functionalities
Key Changes
- Some ALICE Optimize (Core) metrics are now used instead of ALICE Model (Pro) ones, which can potentially cause different solutions to be found for each scenario. However, the types of metrics used remains the same and no significant differences in results are expected.
-
Workdays calculation. In the Model Legacy calculation method, workdays were defined as the number of workdays when at least one crew is actively working on some task with respect to a task calendar. With the migration, workdays are now calculated using the same logic as ALICE Optimize (Core), aligning with Primavera P6 to ensure consistency and improve compatibility across platforms.
-
Specifically, the calculation measures the total number of working hours between the start of the first task and the end of the last task, then divides that by the number of working hours in a day. The calendar used for this calculation depends on task assignments:
- if all tasks use the same calendar, that calendar is applied;
- if tasks use multiple calendars, the project’s default calendar is used.
-
Specifically, the calculation measures the total number of working hours between the start of the first task and the end of the last task, then divides that by the number of working hours in a day. The calendar used for this calculation depends on task assignments:
- Criticality calculation is now unified across ALICE Model (Pro) and ALICE Optimize (Core). Model will adopt the Optimize approach, but resource precedence logic will remain ON by default to maintain current behavior. Users can switch it OFF using a toggle in the Analyze page if they prefer not to include resource logic in the critical path calculation.
Data Migration
- After July 31st 2025, all newly created Model projects and plans will use the upgraded version of Model.
- To bring a project into the new Model experience, duplicate the project and the newly created one will be in the new version of Model.
- It's not possible to migrate solutions (dots) from the old Model experience to the upgraded one. You will need to re-run scenarios after duplicating the project.
- Later this year, projects in the old Model experience will become 'view only' and you'll need to duplicate them to make future changes. This allows us to focus our development efforts on innovation rather than maintaining the old, deprecated version of Model indefinitely.