This article explains the Recipe Matrix template and how to use it in ALICE, including:
- Pages overview
- Recipes: where the user can define the project recipes
- Resource Pool: where the user can define the project resources pool
- Overview of each column in the table
- Inputs needed for each column
- The newest Recipe Matrix template can be downloaded HERE.
Tab 1: Recipes
Here is the columns overview:
Column Letter |
Column Name |
Purpose/Comments |
Example Values |
---|---|---|---|
A |
Recipe Name |
Define Recipe name Determine which operations belong to the same recipe (same value should be used for all operations that belong to the same recipe) |
Typical Concrete Columns |
B |
Recipe Type |
Defines the recipe type: Construction, Demolition, or Temporary |
Construction |
C |
Number |
Reference number that can be used to reference activities while defining precedence relationships (see the Precedence column below) It’s recommended to use a value of “1” for the first activity of each recipe, and then increment from there |
1 |
D |
Operation Name |
This will allow the user to define the names of each operation/task in a recipe. The same name should not be used twice within the same recipe but can be used again in different recipes. E.g.: we may have a “pour” operation in the “concrete slabs” and the “concrete columns” recipes |
Close Forms |
E |
Precedence |
Defines the Predecessor(s) of each operation by referencing the “number” of the preceding operation from the same recipe as well as the relationship type and lag. The “^” and “$” signs can be used to reference the “previous element” and “next element” (aka recipe nodes) respectively. The acceptable relationship types are FS, FF, SS, SF, FaS, FaF, SaS, and SaF. Each relationship should be separated by a comma, and a “+” sign can be used to add lag to each relationship (in hours) |
4FaS+3,$FS |
F |
Subcontractor |
Name of the subcontractor that will be handling the operation on the same row. You may type “No Subcontractor” if there is no subcontractor for this operation (ex: self perform or curing time) Note: Here we start to work with entries that also relate to the resource pool (covered in the next section) |
Concrete Sub |
G |
Crew Type |
Name of the crew from the subcontractor that will be handling the operation in the same row If the general contractor is leading this effort and has no visibility on the different crew types a subcontractor will use, they may use a generic crew type for that subcontractor. However, more detailed information could allow for better optimization as ALICE works through the different possible construction strategies You may type in “No Crew Required” if no crew is required |
Carpenter Crew |
H |
Min. Crews Required |
Minimum number of crews required by the specific task (most common value is 1) This is not related to how many crews you wish to bring on-site for your project. |
1 |
I |
Max. Crews Required |
This number is used when it is possible to assign more crews than the minimum to the same activity in order to complete it faster This should be greater than or equal to “Min. Crews Required” |
3 |
J |
Equipment Type |
Name of the equipment needed This field can be left blank if no equipment is required Multiple Assignments are supported, simply separate each equipment by a “;” |
Excavator; Forklift |
K |
Qty. Equipment Required |
Number of equipment needed Formulas may be typed in this field *Element parameters are currently not supported here For multiple assignments, you may place a single value for all assignments, or separate values by semi-colons in the right order |
1;2 |
L |
Crane Type |
Name of the crane that may service this activity This field can be left blank if no crane is required Multiple Assignments are supported, simply separate the names of the cranes by a semi-colon. |
Tower Crane West |
M |
Material |
Name of the material needed This field can be left blank if no material is required/supplied by the activity *Multiple Assignments are currently not supported |
Formwork |
N |
Action |
Defines whether the Material from the previous column is required or supplied by the activity This may be left blank if no material is supplied/required. Otherwise, the possible values are “requires” and “supplies” |
Requires |
O |
Qty. Material Required |
Quantity of material needed Formulas can be used in this field *Element parameters are currently not supported here |
5 |
P |
Production Rate |
Names of the rate that will be used in any of the duration/quantity formulas Multiple Assignments are supported, simply separate the names of the rates by a semi-colon. |
pour_rate |
Q |
ALICE Duration (hours) |
Duration value in hours Formulas such as: “3*8” or “mat.concrete/pr.concrete_pour” are acceptable values. |
4*8 |
Tab 2: Resource pool
Note: Resources entered in this part of the matrix will only be imported if they are used in a recipe from the previous tab.
Here is the columns overview:
Column Letter |
Column Name |
Purpose/Comments |
Example Values |
---|---|---|---|
A |
Subcontractor |
Name of Subcontractor Use the same value for different crews belonging to the same subcontractor. |
“Concrete Sub” |
B |
Trade |
Subcontractor specialty The same value should be used for the same subcontractor |
“Concrete” |
C |
Crew |
Name of crew |
“Carpenter Crew” |
D |
Qty.Available |
Initially assumed available amount of crews for this project (this can later change while exploring simulations) |
4 |
E |
$/hour |
Cost of 1 crew per working hour |
300 |
F |
Equipment |
Name of Equipment |
Excavator |
G |
Qty.Available |
Initially assumed available pieces of that equipment for this project (this can later change while exploring simulations) |
3 |
H |
$/hour |
Cost per hour of owning/renting a single piece of this equipment. Note: this cost will be charged for 24 hours of each day that the equipment is on-site |
600 |
I |
Cranes |
Name of Crane |
Tower Crane West |
J |
Radius (ft) |
Radius of Crane |
230 |
K |
Move Time (hrs) |
Move (set-up) time for mobile cranes with multiple predefined positions. |
3 |
L |
Qty.Available |
Number of cranes of each type available for this project |
1 |
M |
$/hour |
Cost per hour of owning/renting a crane of this type Note: this cost will be charged for 24 hours of each day that the crane is on-site |
1000 |
N |
Material |
Name of Material |
Formwork |
O |
Type |
Type of material “Consumable” vs “Reusable” |
Consumable |
P |
Qty.Available |
Amount of material initially assumed available for the project |
|
Q |
$/unit |
Cost per unit of the material defined |
300 |
R |
Production rate |
Name of rate Note: when used in formulas, rate names will be prefixed by “pr.” (example: “concrete_pour” becomes “pr.concrete_pour” |
concrete_pour |
S |
Qty/hr |
Value of production rate per hour |
8 |
Comments
0 comments
Please sign in to leave a comment.