Example Duration Formula Library

Intro

This article collects example duration formulas you can copy and adapt in ALICE. Each example pairs a scheduling goal with a formula and the data it needs. To learn how to enter a formula on the Plan page, see Flexible Formulas.

How to read a formula

Formulas combine variables with basic operators: *, /, +, - and parentheses. For variable names, syntax and the formula sidebar, see Building a Flexible Formula.
 

Example formulas

Names in square brackets are placeholders. 

Goal Formula What it needs
A fixed number of work hours shared across crews working in parallel; adding crews shortens the duration 60/num_crews Crews assigned to the task
Imported Activity Duration shared across crews. Adding crews shortens the duration.  Task.imported_duration / num_crews Crews assigned to the task
Time to install a material quantity at a set production rate mat.[material]/pr.[production_rate] A material quantity on the task; a production rate defined in the project
Time to install a material quantity at a set production rate, shared across crews working in parallel mat.[material]/pr.[production_rate]/num_crews Material quantity, production rate, crews assigned
A material quantity shared across crews working in parallel, with no production rate applied mat.[material]/num_crews Material quantity and crews assigned; no rate
The task's Budgeted Labor Units shared across crews working in parallel task.blu/num_crews Budgeted Labor Units on the task; crews assigned
The task's Budgeted Labor Units shared across crews, then converted to time at a set production rate task.blu/num_crews/pr.[production_rate] Budgeted Labor Units; crews assigned; production rate
A fixed number of work hours shared across equipment working in parallel; adding equipment shortens the duration 60/eq.[equipment] Equipment assigned to the task
Duration driven by two custom fields on the task: total volume over number of elements task.udf.[field_1]/task.udf.[field_2] Both custom fields filled in on the task
Duration driven by the same two custom fields, shared across crews working in parallel task.udf.[field_1]/task.udf.[field_2]/num_crews Both custom fields; crews assigned

 

Worked example

Placing concrete. A slab task needs 600 cubic yards of concrete. The project's concrete production rate is 30 cubic yards per hour, and two crews are assigned.

In the duration formula, enter:

mat.concrete/pr.concrete_rate/num_crews

ALICE calculates 600 / 30 / 2 = 10 hours Task Duration.

Double the crews assigned to 4 and reschedule. ALICE recalculates 600 / 30 / 4 = 5 hours Task Duration.

Things to know

  • Duration formulas work only on not-started tasks. In-progress and completed tasks, and milestones, keep static durations.
  • After you change a variable, reschedule the plan to update durations.
  • To round calculated durations up, set an interval in the table view settings.
  • To see the formula behind each duration, add the Remaining duration formula column.
  • When you export plan data to Excel and import it back, ALICE applies the duration formulas in the file.
  • When you upload a new version from P6 or MSP with the Duration formulas option on (the default), tasks keep their ALICE formula. A number typed in ALICE is not a formula, so the new file's duration replaces it. Reschedule after the sync to see formula-driven durations.

Insights Agent

You can also ask the ALICE Insights Agent to help you build a duration formula.

 

Was this article helpful?
1 out of 1 found this helpful